Responding to a resident’s social media post about a new restaurant in Hermanus’ historic Old Harbour, an Overstrand Municipality official explained that the required land-use application underwent public participation in 2024, and building plans were approved in July this year.
The resident who raised the issue questioned the need for another restaurant at the harbour, arguing that residents should have a say in development affecting Hermanus’s historic character and natural beauty.
According to Acting Municipal Manager Edward Jantjies, the municipality received a land-use application on 7 November 2023 from an architect acting on behalf of the Old Harbour Museum Trust, the property owner. The application sought consent to operate a restaurant as a tourist facility on Erf 6119 in Marine Drive.

Public participation began on 16 February 2024, with 30 days for comments and objections. Notices were on the municipal website, displayed on the property, and sent to neighbouring owners via the Hermanus Ratepayers’ Association and ward councillors.
“No comments or objections were received during this period,” Jantjies said.
The application was also circulated to the provincial Department of Environmental Affairs and Development Planning, including its Coastal Management division, and relevant municipal departments for input.
Although the building is not classified as a heritage building, the property is a Grade II heritage site. Heritage Western Cape issued a permit under Section 27 of the National Heritage Resources Act on 30 January 2024, following consideration by the Overstrand Heritage and Aesthetics Committee.
The Municipal Planning Tribunal approved the land-use application on 31 October 2024, subject to conditions, including compliance with approved development plans, building-plan approval and heritage-related requirements.
Building plans – including architectural drawings and supporting documents – submitted on 12 June this year, were approved on 14 July. Jantjies said the plans were assessed against the National Building Regulations and Building Standards Act and other applicable legislation. This approval process does not require a separate public participation process.
The project involves adapting existing structures, internal alterations and adding an external wooden deck. The buildings will be retained, with no major structural changes planned. Construction has commenced in accordance with the approved plans.
The municipality said the Old Harbour Museum Trustees, a private entity, owns the property and leases several buildings to generate income for the museum’s ongoing maintenance and operation.